An Amazonian City, USA

Jan 28, 20

An Amazonian City, USA

The World’s Largest Internet Retailer Updates Seattle’s Skyline with a Unique Neighborhood

Amazon has become the first place consumers go to shop for almost anything. In its hometown of Seattle, the corporation has taken over 3.3 million square feet (306,580 m2) on three city blocks to create an Amazon neighborhood for its 55,000 Seattle employees. Located in the Denny Regrade Triangle in downtown Seattle, the campus consists of three 37-story high-rise office towers, two mid-rise office buildings, and a multipurpose meeting center in the shape of three glass domes. The glass domes, called “the Spheres,” opened to the public and Amazonians at the end of January 2018. Putzmeister’s BSA 14000 HP-D4 8" and BSA 2110 HP-D4 Trailer Pumps; MX 36/40 Placing Boom; 20Z-, 31Z-, 40Z-, 47Z-, 56Z-, 61Z-, 63Z-Meter Boom Pumps were all utilized to bring the project to fruition.

General contractor Sellen called upon Brundage-Bone Concrete Pumping’s Kent, Washington location to handle the operation’s concrete needs. Brundage-Bone was all hands on-deck, bringing their best fleet to the job site.

“When you ask an operator what they want to operate, it’s typically Putzmeister,” said Mark Young, Brundage-Bone National Fleet Manager. “They have the features that make their lives easier.”


The First of Three

Construction began on the first building, which was named Doppler after Amazon’s internal code name for Alexa, in 2013. Designed by Seattle architecture firm NBBJ, the building is 1 million square feet (93,000 m2) and includes a five-story meeting center, parking garage and 36 additional floors of office space, eateries and employee amenities.

A job site in the middle of a bustling city presents contractors with extra challenges, including space restrictions and street permits required by the city. Depending on the city, these permits can become very expensive and/or restrictive. In the case of Seattle, it was the latter; the job site for Amazon’s neighborhood allowed for a tight set up of only 9 m wide.

“A congested city block always makes things a little more difficult,” said Shawn Jameson, operations and placing boom manager at Brundage-Bone. “Putzmeister’s boom pumps are configured to minimize the footprint.”

The 11,000 cubic yard (8,400 m³) mat pour began with the large boom pumps. As construction on the building continued to reach higher stories, Brundage-Bone added a MX 36/40 placing boom to the site. With a tight set up, the crew used the horizontal reach on the boom pump up to 204 feet (62 m) before needing to switch to a placing boom. The tower, used in conjunction with an adapter, was able to free stand 80 feet (24 m). Other placing booms were mounted on the core wall with an x-frame on top of a wall climbing system.

“Our equipment was put to the test with this pour,” Jameson said.


Up to the Test

Day One, the second of the three high-rise buildings, includes office space, meeting space, a parking garage, various restaurants, and employee amenities. The name of the building comes from the founder of Amazon, Jeff Bezos. He has been known to say every day at Amazon is “Day One” because there is always something new to experiment, innovate or invent.

The construction on Day One also pushed General Contractor Sellen to break a company record. The 1.5 million square foot (139,855 m2) building required the largest concrete mat pour in their history.

“The pour took 12 hours and we were able to complete the entire pour without a single mechanical error,” Jameson said.

A 61Z-Meter and 63Z-Meter boom pumps were used to complete the 11,700 cubic yard pour (8,945 m³). The One-Sided Support (OSS) outrigger system on these large pumps allowed the operator to reduce the outrigger extension on one side of the unit to create a smaller overall machine footprint.

“The outrigger configuration and ease of placing boom equipment was incredibly important for this particular job,” Jameson said.

The tower opened to Amazon’s employees and the public in November 2016, and sits adjacent to the Spheres.


A Relaxing Spot to Get Away

The most recently finished Spheres are a marvel on the city block. They sit in the middle of Amazon’s neighborhood as a place for employees to getaway and relax. They contain tens of thousands of plants and trees from around the world. Since their unveiling in late-January 2018, they have been delighting visitors.

"Our goal with The Spheres was to create a unique gathering place where employees could collaborate and innovate together," said Amazon vice president John Schoettler in a statement. “From the moment we started construction, people would stand on the street corners taking photographs.”

The largest sphere is 130 feet (40 m) in diameter and is flanked by two smaller spheres on either side. The incredible structures created site challenges of their own – narrow openings and low clearances. A 31Z-meter boom pump was crucial to the pour for its flexibility and maneuverability. It can be strategically positioned for precise concrete placement in unusual job sites, like the Denny Regrade Triangle. The smaller pump was able to reach through the glass window openings to pour a concrete wall that today is home to thriving vegetation.

“As the centerpiece of this truly amazing workplace, we knew our equipment could get the job done accurately and efficiently,” Jameson said.

Poured with white concrete in conjunction with a lot of artistic shotcrete for a very unique look and feel, the Spheres contain 620 tons (62 metric tons) of steel, 5 million kg of concrete and 2,643 panes of glass. The shotcrete was sprayed using a Thom-Katt® TK 50 trailer pump.


Changing the Skyline

The final building to complete the neighborhood, Block 20, is sized at 1.6 million square feet (148,645 m2) and is said to reshape the Seattle skyline. The building is scheduled for completion in late 2019. Brundage-Bone poured 30,670 feet (9347 m) of concrete for the mat footing in July 2017 using a variety of concrete equipment. The office building will be a 45-story building constructed of a steel structure with a concrete core and decks. When the building is finished, Brundage-Bone will have poured nearly 269,040 feet (82,000 m) of concrete.

“I’ve worked with Putzmeister concrete pumps for 20 years,” said Joshua Armstrong of Brundage-Bone. “They’re the best pumps I’ve ever run.”


Conclusion

When the neighborhood is completed in 2021, a grand total of 820,240 feet (250,000 m) of concrete between three buildings will have been poured. The new Amazon headquarters will change the Seattle skyline and Denny Regrade Triangle neighborhood, and it will give employees of the largest Internet retailer a new place to call home. The project continues to progress day-by-day, and with Brundage-Bone and their fleet, the project continues to go off without a hitch.

 

Brundage-Bone poured the mat for the Amazon’s Spheres. The Spheres serve as a relaxing getaway for its 55,000 Seattle employees.

Brundage-Bone’s Kent, WA location brought its entire Putzmeister fleet to the Amazon site including the 47Z-Meter Boom Pump.

Amazon changed Seattle’s skyline with the help of Putzmeister customer, Brundage-Bone.

A job site in the middle of a busy city presents extra challenges for the crews.

Inside Amazon’s Block 20 pour.

Large boom pumps are used to reach long distances to avoid moving equipment.

 

Owner: Amazon – Seattle, Washington

Developer: Acorn Development, LLC.

General Contractor: Sellen – Seattle, Washington

Ready-Mix Supplier: Stoneway Concrete – Renton, Washington

Equipment Supplier: Brundage-Bone – Kent, Washington

Putzmeister Equipment: 
BSA 14000 HP D4 8" Trailer-Mounted Pump
BSA 2110 HP D4 Trailer-Mounted Pump
MX 36/40 Placing Boom
20-Meter Boom Pump
31-Meter Boom Pump
40-Meter Boom Pump 
47-Meter Boom Pump
56-Meter Boom Pump
61-Meter Boom Pump
63-Meter Boom Pump