Oakland Bay Bridge: World's Largest Concrete Boom Pump on a Historic Project, USA

20/02/27

Oakland Bay Bridge: World's Largest Concrete Boom Pump on a Historic Project, USA

After a three-week trek by ship and 16,000 km, Associated Concrete Pumping’s (Associated) Putzmeister 70-Meter, the world’s largest truck-mounted concrete boom pump, arrived in San Diego harbor from Aichtal, Germany. Soon after its arrival, the “Juggernaut” as the pump is often referred to, took concrete placement to the extreme on the Oakland Touchdown (OTD) – Phase 1 section of the San Francisco – Oakland Bay Bridge project, helping to place 1,988 m3 of concrete, along with Associated’s 63- and 46-Meter boom pumps.

In 1989, a section of the East Span of the Bay Bridge was damaged during the 6.9 magnitude Loma Prieta earthquake. Following the earthquake, extensive studies were undertaken to determine whether California’s largest bridges were seismically safe. It was determined the entire Bay Bridge required a seismic retrofit, ultimately reinforcing and rebuilding each section of the bridge.

Work on the seismic retrofit of the bridge began in 2001, and in August 2008, MCM Construction (MCM), the general contractor on the OTD - Phase 1 section of the project, arrived on site and work quickly began.

Two phases comprise the OTD section. The first phase includes construction of approximately 305 m of the westbound approach roadway, from the toll plaza to the Skyway, as well as approximately 152 m of the structure for the eastbound roadway. The second phase includes finishing construction of the roadways.

“Once complete, the Oakland Touchdown will connect Interstate 80 in Oakland to the two new side-by-side roadway decks of the new East Span,” comments Bart Ney, State of California Department of Transportation’s (CalTrans) public information officer. “A new electrical substation will be built in addition to extensive relocation of underground utilities.

“For westbound drivers on Interstate 80, the Oakland Touchdown will be an introduction to the new East Span of the Bay Bridge, and for the eastbound drivers from San Francisco, it will guide them from the Skyway to the East Bay.”

In addition to the OTD, six other sections of the San Francisco-Oakland Bay Bridge are undergoing seismic retrofits, making the project the largest public works contract for CalTrans, the owner/developer of the project. The other six sections include the West Approach, West Span, Yerba Buena Island Transition Structure, SAS span, Skyway and East Span Demolition.

 

A “Juggernaut” of a Job

According to Greg Allen, project manager for MCM, everything about the San Francisco – Oakland Bay Bridge project is super-sized, including the OTD’s foundations, the design of the bridge itself, and the 70-Meter concrete pump.

“The foundations are 2 m in diameter, 52 m long and 89 mm,” says Allen. “And the design of the bridge superstructure features a sloped soffit combined with deck cross falls which created challenging geometry control. To provide easier access for the boom pumps and other construction equipment on this project, a trestle was built between the eastbound and westbound roadways.

In addition, the eastbound and westbound roadways are both 12 m high by 24 m wide. The job required boom pumps that provided exceptional reach to pump and place the concrete for the stem and soffit sections of the OTD precisely where it needed to be.

“We chose Associated because of their notable reputation within the concrete construction industry and the capabilities of their wide range of innovative equipment,” comments Allen. “Given the size of the bridge and the other job site obstacles, we were looking forward to seeing how the world’s largest truck-mounted concrete boom pump would fare on this site.”

“What better way to initiate the 70 manufacturing feat than have it pump and place concrete for a historic project like the San Francisco-Oakland Bay Bridge?” asks Mike Parigini, owner of Associated and the first 70 boom pump. During the design phase of the unit, Parigini was instrumental in providing useful customer feedback and input to Putzmeister.

The 70, along with Associated’s 63- and 46-Meter were on site for the 10-hour concrete pour for the OTD westbound roadway’s stems and soffits in January 2009. Although the 70Z has been on other jobs since arriving on U.S. soil, the San Francisco – Oakland Bay Bridge was the first big project that showcased its impressive technological features.

“We were definitely impressed all around with the performance of the 70 on this pour, especially in terms of its reach and pumping capacity capabilities,” notes Allen.

“With the 70’s five-section Z-Fold boom, it’s all about its flexible 69.3 m vertical and 64.9 m horizontal reach, and being able to get where you don’t have to drag any hose,” says Parigini. “We can deploy the boom in either a ‘Z’ position or an ‘A’-frame configuration. Concrete is very heavy, so to move it anywhere at any speed without using a lot of labor is a huge time and cost saver for all involved with the project. The unit’s 10 axles come off the ground to steady its 79,832 kg weight.”

“The combination of its reach and up to 160 m3/hr of volume output at 1,233 psi, the 70 was able to pump and place a large amount of the total  1,988m3 of concrete for this pour without having to move to different locations on site, which would have increased the amount of time the pour would have taken,” adds Allen.

“The 70 features a modular bolt-on flatpack and Putzmeister’s exclusive free flow hydraulics which ensured continuous smooth pumping and a consistent concrete flow for this pour,” notes Parigini.

Parigini continues, “One of the biggest misconceptions about a boom pump of this size is that it’s not easily maneuverable on job sites, but really, it is. The 70 has a 18 m outside turning radius which allowed us to easily navigate the unit around the restrictive job site.”

The unit was also designed to pass California’s strict “purple permit” weight requirements, which makes it fully licensed for the road.

“With the 70 cleared to hit the road, we don’t have to worry about not being able to use the pump in only certain jurisdictions,” comments Parigini.

“Our five-section 63-Meter and 46-Meter teamed up with the 70 to get the job done,” notes Parigini. “The 63’s Z-Fold boom 62.10 m vertical reach and 58.09 m horizontal reach helped tremendously to keep the job moving smoothly, along with its up to 200m3/hr volume output. The 46-Meter’s horizontal reach is 41.50 m, and its vertical reach is 45.20 m.

The 63 was on site previously to the January 19th pour pumping and placing concrete for the OTD – Phase 1 section.

According to Parigini, both the 70 and 63-Meter concrete pumps feature Putzmeister’s Ergonic® system which allowed his operators to set parameters that control the boom, the pump and a variety of operational functions on the OTD project site. The system is easily accessible in the Modular Control Box (MCB) on the units.

“This technology includes the Ergonic Pump System,” explains Parigini. “This optimizes the pump and other functions and Ergonic Output Control, which reduces fuel consumption, wear, noise and adjusts the engine speed to the delivery rate. In addition, Ergonic Boom Control controls the boom, and Ergonic Tele Service can be used in case remote diagnosis is needed for fault codes. There is also an Ergonic Graphic Display, a three-inch square LCD screen on the MCB that indicates the unit’s hydraulic fluid temperature, operating hours, delivery pressure/delivery pressure limit and delivery rate/delivery rate limit.”

In addition to the super-sized characteristics of this project, the concrete mix that was pumped and placed by all three concrete pumps was unique as well. “The concrete mix was a low-shrinkage design with a high strength at 43 Mpa at 7 days,” says Ney.

The 70, 63 and 46-Meter will be on and off the OTD section of the project for miscellaneous concrete needs. The OTD project is slated for completion in May 2010.

To learn more about the 70-Meter boom pump, check out the new Putzmeister 70-Meter DVD on YouTube at: http://www.youtube.com/PutzmeisterAmerica.

The 70’s 10 axles come off the ground to steady its 79,832 kg weight.

Together, Associated’s 70-, 63- and 46-Meter pumped and placed 1,988 m3, of concrete for the OTD – Phase 1 soffits and stems in 10 hours.

All three concrete pumps boasted impressive horizontal and vertical reaches as well as volume output capacity on site.

Associated’s 63- (in foreground) and 70 (in background) both feature Putzmeister’s exclusive Ergonic® technology.

The 70 has a 18 m outside turning radius which allowed Associated to easily navigate the unit around the restrictive OTD job site.

The eastbound and westbound roadways of the OTD are both 12 m high by 24 m wide, so the job required boom pumps that provided exceptional reach to pump and place the concrete for the stem and soffit sections of the OTD precisely where it needed to be.